El Camino High School - Gas Piping Replacement

A leak was discovered due to degraded glue in plastic piping.  The leak was repaired in March 2017.

Complete replacement of all site gas piping took place during summer 2018 to prevent future leaks.

McAuliffe Elementary School - Playground Upgrades

Kinder, primary and secondary playgrounds all had drainage problems.

Complete reconstruction of all playgrounds with proper drainage took place during summer 2018.

Reynolds Elementary School - Playground Upgrades

Kinder, primary and secondary playgrounds all had drainage problems.

Complete reconstruction of all playgrounds with proper drainage took place during summer 2018.

El Camino High School - Softball Field Upgrade

Phase I: upgrade current varsity field for future JV use with new backstop, dugouts, and infield surface.

Phase II: build new varsity field with concrete block dugouts on new site; cover current JV field with new grass.

Construction is planned for summer 2019.